Exception requests that span extensive lengths of time are not fully granted because the wildlife staff cannot adequately analyze impacts over such long periods of time. Such requests are sometimes given partial grants that enable work over shorter periods of time and are then reevaluated for extensions to the original exception. This table includes the original request and each extension evaluated for each location.
| |
COA |
Company |
Location / Wells |
Requested Action |
Action Date |
Action Status |
Requested Dates |
Dates Excepted |
Lease/ROW |
Town(N) |
Range(W) |
Sec. |
Remarks |
1 |
|
QEP |
Mesa 12-8 |
|
|
|
|
|
|
|
|
|
|
2 |
|
QEP |
Mesa 11-9 |
|
|
|
|
|
|
|
|
|
|
3 |
|
Enterprise |
Boulder 5-19 Pipeline |
|
|
|
|
|
|
|
|
|
|
4 |
Antelope Crucial Winter Range |
PacifiCorp |
Anticline Electrification |
Setting structures & anchors, pulling a& tensioning, reclamation |
11/01/12 |
Granted |
11/15/12 thru 12/31/12 |
11/15/12 thru 12/31/12 |
W-179388 |
30, 31 |
108, 109 |
Var. |
Helicopter time to be keep to a minimum and before 11/20. |
5 |
|
SWEPI LP |
Riverside 2-24 |
|
|
|
|
|
|
|
|
|
|
6 |
Antelope Crucial Winter Range |
SWEPI LP |
Mesa 12-14 -WB Gathering Facility |
Reroute approximatley 390' of 12 inch produced water line. |
11/27/12 |
Granted |
12/10/12 thru 1/10/12 |
12/17/12 thru 01/17/13 |
WYW-172126 |
30 N., |
109 W., |
14 |
Corrosion could cause current carbon steel pipeline to fail. |
7 |
Big Game Crucial Winter Range |
Ultra |
Boulder 5-30 Pipeline Amendment |
Installation of pipeline from Bldr 5-30 to RS 4-25 Access Road |
02/01/13 |
Granted |
11/15/12 thru 4/30/2013 |
|
WYW-178613 am2 |
31 |
108/109 |
25/30 |
Existing disturbance |
8 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 9-8 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
5/29/2013 thru 11/30/2014 |
|
WYW-08589 |
32N |
109W |
8 |
|
9 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 11-9 |
Setting facilities, piplines, construction, and completions |
|
|
2/21/2013 thru 11/15/2014 |
|
WYW-08589 |
32N |
109W |
8 |
|
10 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 5-8 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
4/1/2013 thru 11/30/2014 |
|
WYW-08589 |
32N |
109W |
8 |
|
11 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 15-9 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
2/21/2013 thru 11/30/2013 |
|
WYW-015317 |
32N |
109W |
9 |
|
12 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 11-7 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
2/21/2013 thru 11/15/2014 |
|
WYW-15315, 08589 |
32N |
109W |
7 |
|
13 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 7-8 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
2/21/2013 thru 11/15/2014 |
|
WYW-15315, 08589 |
32N |
109W |
8 |
|
14 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 3-17 |
Setting facilities, piplines, drilling mud plant, construction,, water staging, and completions |
|
|
2/21/2013 thru 11/30/2013 |
|
WYW-15315, 08589 |
32N |
109W |
17 |
|
15 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 7-18 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
2/21/2013 thru 11/30/2013 |
|
WYW-15315 |
32N |
109W |
18 |
|
16 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 6-7 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
2/21/2013 thru 11/15/2014 |
|
WYW-15315, 08589 |
32N |
109W |
7 |
|
17 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
QEP |
Mesa 3-7 |
Setting facilities, piplines, construction, cuttings solidification, and completions |
|
|
4/1/2013 thru 11/30/2014 |
|
WYW-15315, 08589 |
32N |
109W |
7 |
|
18 |
Big Game, Sage Grouse Winter, Nesting and Early Brood Rearing |
EJGG |
Riversiide 9-24 |
Installation of 3700' x 50' P/L to connect Ultra's additional wells |
02/20/13 |
Granted |
03/6/2013 thru 05/15/2013 |
03/06/13 thru 05/15/13 |
WYW-179570,179571 |
31N |
108W |
19 |
|
19 |
Big Game |
Ultra |
BR 15-18 to CGF #2 |
Installation of 151' X 50' pipeline for sale of flash gas |
03/01/13 |
Granted |
3/4/2013 thru 3/8/2013 |
3/4/13 thru 03/08/2013 |
WYW-179577 |
31N |
108W |
19 |
|
20 |
Burrowing owl |
EnCana |
SHB 123-32 & 124-32 |
Finish completions through April 15, 2013 |
03/29/13 |
Exception not needed |
April 1-15, 2013 |
|
WTW125944 |
29N |
108W |
32 |
Exception not needed. On private land, BLM enforcement limited. Central frac pad is outside 1/2-mile, but the pad being fracked is about 3/8 mile from nest. EnCana expects to be done by April 5, but asked for April 15, just in case things do not go perfectly. |
21 |
Big Game, Sage grouse Nesting and Early Brood Rearing |
Sublette County |
Dry Basin gravel pit |
gravel mining/hauling |
04/22/13 |
Partially granted |
April 15, 2013 - July 15, 2013 |
May 15 - July 15 |
WYW175468 |
28N |
113W |
3 |
Pit Run needed to widen Calpet Road |
22 |
Wildlife Stipulation |
Ultra |
Mesa 9-21 |
Wildlife Stipulation Request |
03/26/13 |
Granted |
03/26/2013-06/15/2013 |
Big game11/15/13 to 04/30/13 SageGrouse 03/15/13 to7/15/13 |
WYW135125 |
32N |
109W |
21 |
Request granted |
23 |
Sage grouse |
SWEPI LP |
Rainbow 13-29 |
Dirt work for interim reclamation |
|
|
5/20/13 - 6/7/13 |
|
WYW118148 |
30N |
107W |
29 |
|
24 |
Ferrug. Hawk, Burrowing owl |
SWEPI LP |
Mesa 11-34 |
Dirt work for interim relcamation |
|
|
5/22/13 - 6/12-13 |
|
WYW06286 |
32n |
109w |
34 |
|
25 |
Big game, Sage grouse |
QEP |
Stewart Point 14-32 |
Pad construction before drilling |
|
|
June 1 to July 15, 2013 |
|
WYW08589/08592/015315 |
33N |
109W |
32 |
part of the 6-mile CDA allowed by ROD |
26 |
Sage grouse and Raptor |
ExxonMobil |
Fogarty Creek 19-35 |
P&A wellbore |
05/16/13 |
Granted |
June 20 to July 31, 2013 |
|
WYW0320214 |
29N |
114W |
35 |
COA to plug Idle sour gas well and limited rig availability |
27 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 106-35 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 106-35 |
12/12/12 |
Granted |
Dec. 15, 2012 to April 30, 2013 |
Dec. 15, 2012 to April 30, 2013 |
WYW100902 |
29N |
108W |
35 |
|
28 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 18-32 and 84-32 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 18-32 and SHB 84-32 well pads. |
11/30/12 |
Granted |
Nov. 19, 2012 to April 30, 2013 |
Nov. 19, 2012 to April 30, 2013 |
WYW125944 |
29N |
108W |
32 |
|
29 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 39-35 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 39-35/ SHB 96-35/ SHB 85-35 three well pad. |
12/07/12 |
Granted |
Dec. 15, 2012 to April 30, 2013 |
Dec. 15, 2012 to April 30, 2013 |
WYW100902 |
29N |
108W |
35 |
|
30 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 41-33/99-33 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 41-33 and SHB 99-33 two well pad. Start date is Nov. 25th. |
11/30/12 |
Granted |
Nov. 25, 2012 to April 30, 2013 |
Nov. 25, 2012 to April 30, 2013 |
WYW125944 |
29N |
108W |
33 |
FM Comments: WGF supports granting. Studies have not demonstrated adverse effects. |
31 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 58-33 / 124-33 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 58-33 and SHB 124-33 two well pad. Start date Nov. 27th. |
11/30/12 |
Granted |
Nov. 25, 2012 to April 30, 2013 |
Nov. 25, 2012 to April 30, 2013 |
WYW125944 |
29N |
108W |
33 |
|
32 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 89x-33 / 85-33 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 58-33 and SHB 124-33 two well pad. Start date Nov. 27th. |
11/26/12 |
Granted |
Nov. 20, 2012 to April 30, 2013 |
Nov. 20, 2012 to April 30, 2013 |
WYW125944 |
29N |
108W |
33 |
FM Comments: Reference G&F letter dated 11/15/12. This exception request is within a densely developed area. Also reference email exchange (11/16 to 11/20) between FM and BLM bio. |
33 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 109-33 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 109-33 well pad. |
01/22/13 |
Granted |
Feb. 1, 2013 to April 30, 2013 |
Feb. 1, 2013 to April 30, 2013 |
WYW125944 |
29N |
108W |
33 |
|
34 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 123-32 / 124-32 |
Construct (pad and pipeline), Drill, Complete and produce the SHB 123-32 / SHB 124-32 two well pad. |
11/30/12 |
Granted |
Dec. 1, 2012 to April 30, 2013 |
Dec. 1, 2012 to April 30, 2013 |
WYW125944 |
29N |
108W |
32 |
|
35 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 127-33 |
Construct, Drill and Complete the SHB 127-33 Jonah Gas well. Including: pad construction, pipeline installation, fuel gas installation, Drilling, completions work and facility installation. |
11/13/12 |
Granted |
Nov. 17, 2013 to Jan. 1, 2013 |
Nov. 17, 2012 to Jan. 1, 2013 |
WYW125944 |
29N |
108W |
33 |
WGF has been consulted. They are not concerned with adverse pronghorn effects. Intensive development has been in place for several years even while crucial winter range use has occurred. Local pronghorn monitoring is well as observations suggests pronghorn tolerance for development. |
36 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 81-33 |
Construct (Pad and Pipeline), Drill, complete and produce, the SHB 81-33 well pad. |
12/21/12 |
Granted |
Dec. 26, 2013 to April 30, 2013 |
Dec. 26, 2012 to April 30, 2013 |
WYW125944 |
29N |
108W |
33 |
Per discussions with WGFD the CWR to protect pronghorn will not be applied to heavily developed portions of the Jonah Field (where the SHB 81-33 is located). |
37 |
Big Game Crucial Winter Range (Pronghorn) |
EnCana |
Stud Horse Butte 93-33 / 104-33 |
Construct (Pad and Pipeline), Drill, complete and produce, the SHB 93-33 / 104-33 two well pad. |
01/22/13 |
Granted |
Feb. 1, 2013 to April 30, 2013 |
Feb. 1 2013 to April 30, 2013 |
WYW125944 |
29N |
108W |
33 |
|
38 |
Sage grouse and Raptor |
Exxon Mobil Corp. |
Fogarty Creek 19-35 |
P+A Fogarty Creek Unit 19-35 well. Surface is Fee, BLM Minerals. Rig scheduled to move on location last week of May. Begin plugging around June 1, 2013. Plan calls for 21 work days. Operator requested permission from WOGCC to leave surface equipment on location for furture utility. |
06/05/13 |
Granted |
|
June 20, 2013 to July 31, 2013 |
WYW0320214 |
29N |
114W |
35 |
|
39 |
Sage grouse and Raptor |
EOG Resources |
NLBSU 7-8 |
Plug well during timing stipulations |
07/09/13 |
Denied |
June 24th-July 31st, 2013 |
|
WYWE07671B |
27N |
113W |
8 |
|
40 |
Sage grouse |
EOG Resources |
NLBSU 33-8E |
Plug well during timing stipulations |
07/09/13 |
Denied |
June 24th-July 15th, 2013 |
|
WYWE07671B |
27N |
113W |
8 |
|
41 |
Sage grouse |
EOG Resources |
NLBSU 32-8E |
Plug well during timing stipulations |
07/09/13 |
Denied |
June 24th-July 15th, 2013 |
|
WYWE07671B |
27N |
113W |
8 |
|