U.S. DEPARTMENT OF THE INTERIORBUREAU OF LAND MANAGEMENT
Wyoming

2009-2010 Wildlife Exceptions

Exception requests that span extensive lengths of time are not fully granted because the wildlife staff cannot adequately analyze impacts over such long periods of time. Such requests are sometimes given partial grants that enable work over shorter periods of time and are then reevaluated for extensions to the original exception. This table includes the original request and each extension evaluated for each location.

COA Legend
BO = burrowing owl
FEHA = ferruginous hawk
BG CWR = big game crucial winter range
SG = sage grouse
CWR = crucial winter range
BE = bald eagle

For further information or to obtain copies of completed documents, please contact John Huston at 307-367-5385.
updated August 18, 2010
Number
COA Company Location / Wells Requested Action Action date Action Status Requested dates Dates excepted Lease/ROW Town(N) Range(W) Sec. Remarks
1
SG, BG CWR, FH SWEPI LP Mesa 13-35 construction, drilling, completions, facility maintenance 02/25/10 Granted 02/25/2010 to 08/2010 02/25/2010 to 08/2010 WYW 015314 32 109 35  
2
SG, BG CWR, FH Questar Mesa 3-21 Drlling, completions, set facilities, install flow lines, gathering facilities 10/28/09 Granted 02/25/2010 to 08/2010 02/25/2010 to 08/2010 WYW 015317 32 109 21  
3
BG CWR, FH SWEPI LP Mesa 1-27 construction, drilling, completions, facility maintenance 11/15/09 Granted 11/15/09 to 04/30/2010 11/15/09 to 04/30/2010 WYW 116265 32 109 27  
4
BG CWR, SG SWEPI LP Mesa 12-28 construction, drilling, completions, facility maintenance 04/01/10 Granted 04/01/2010 to 07/15/2011 04/01/2010 to 07/15/2011 WYW 118165 32 109 28  
5
BG CWR, SG SWEPI LP Boulder 11-19 construction, drilling, completions, facility maintenance 10/01/09 Granted 10/01/2009 to 03/2010 10/01/09 to 03/01/2010 WYW 144993 31 108 19  
6
BG CWR, SG Questar Mesa 7-22 construction, drilling, completions, install flow lines, gathering facilities 10/08/09 Granted 10/08/09 to 07/15/2010 10/26/09 to 07/15/2010 WYW 015317 32 109 22  
7
BG CWR, SG Questar Mesa 8-19 construction, drilling, completions, install flow lines, gathering facilities 10/08/09 Granted 10/08/09 to 07/15/2010 10/26/09 to 07/15/2010 WYW 015315 32 109 19  
8
BG CWR SWEPI LP North LGS Facility complete construction 11/15/09   11/15/09 to 04/30/2010   WYW 176891 31 109 3  
9
BG CWR Cimarex Riley Ridge 20-14 Finish Drilling and rig down 11/12/09 Partial 11/15/09 to 12/01/09 11/15/09 to 12/1/09 WYW 60620,59398 29 114 17  
10
BG Questar Stewart Point et al Construction of pad and pit, set trench boxes, install cellars, move casing 11/10/09 denied 11/15/09 to 12/01/09           SP 14-32, SP 11-21, SP 5-17, SP 12D4-29, within delineation area of DA 1
11
BG CWR, BEWinter Town of La Barge east of town Drill 20 test holes and 1-3 wells for potential water supply 11/12/09 Granted 11/15/09 to 12/12/09 11/15/09 to 12/12/09 WYW 172096 26 112 5  
12
BG CWR Exxon Fiber Optic Line Install overhead fiber optic lines 11/16/09   11/15/09 to 11/30/09   not given 28 114 10,15,20,21,22,27,28  
13
BG CWR Questar Mesa 15-20 completion and flowback equip and activities 11/01/09 Granted 11/01/09 to 12/01/09 11/01/09 to 12/01/09 WYW 015315 32 109 29, 20 Within DA 1 CDA
14
BG CWR Questar Mesa 8-19 completion and flowback equip and activities 11/01/09 Granted 11/01/09 to 12/01/09 11/01/09 to 12/01/09 WYW 015315 32 109 19 Within DA 1 CDA
15
BG CWR Questar Mesa 12-21 equipment and activities necessary for full interim reclamation 11/01/09 Granted 11/01/09 to 11/22/09 11/01/09 to 11/22/09 WYW 015315 32 109 21 Within DA 1 CDA
16
BG CWR Questar Mesa 16-19 completion and flowback, install flow lines, install gather lines, install gas pipeline LGS QGM ROW WYW 176921, 176920, 176919 11/03/09 Granted 11/03/09 to 07/15/09 11/03/09 to 07/15/09 WYW 015315 32 109 19 Within DA 1 CDA
17
BG CWR, SG Questar Mesa 3-22 pad construction pad expansion, drilling, completions, install flowlines, install gather lines, production facillities, pipeline, LGS, QGM loop line 11/03/09 Granted 11/03/09 to 07/15/09 11/03/09 to 07/15/09 WYW 015317 32 109 22, 15 Within DA 1 CDA
18
BG CWR Questar Mesa 8-30 pad equipment and complete installation water disposal facility and cleanup 11/01/09 Granted 11/01/09 to 11/22/09 11/01/09 to 11/22/09 WYW 160992 32 109 30 Within DA 1 CDA
19
BG CWR SWEPI LP North LGS Facility complete construction 11/15/09 Granted 11/15/09 to 04/30/10 11/15/09 to 04/30/10 WYW 176891 31 109 3 Within Core DA2
20
BE roost & BG CWR SWEPI LP Central LGS pipeline finish reclamation of LGS 11/01/09 Granted 11/01/09 to 12/01/09 11/01/09 to 12/01/09 WYW 17793, 176794,WYW 176768, 176769, 176779, 176780, 176760, 176778, 176770, 176661, 176772, 176663, 176774,WYW 176785, 176786, 176787, 176788, 176789, 176790, 176795, 176796, 176770, 176771, 176772, 176773, 176774 31 109 and 108 S 13, 14, 23, and 24 T 31N R109W,S 19, 29, 30, T31N R108 W and S 13, 14, 24, 25, T31N R109W,S 19, 29, 30, T31N R108 W and S 13, 14, 24, 25, T31N R109W To bring vegetation back in delineation area
21
BG CWR SWEPI LP North LGS Facility, Mesa 7-29 install pipe racks for LGS, install piping, tubing, cable trays, and installation 11/15/09 Granted 11/15/09 to 12/01/09 11/15/09 to 12/01/09 WYW 118165 32 109 29 Within Core DA2
22
BG CWR SWEPI LP Boulder 11-19 completion 03/01/09 Granted 03/01/10 to 03/14/10 03/01/10 to 03/14/10 WYW 144993 31 108 19 no extension into SG nesting
23
BG CWR Questar Mesa 6-5, Mesa 6-7, SP, 1-29, SP 5-17, SP 14-32, SP 12-29, SP 11-21 Construction of pad and pit, set trench boxes, install cellars, move casing 11/15/09 Granted 11/15/09 to 12/01/09 11/15/09 to 12/01/09         Denial rescinded due to ability to complete delineation by 2010 and BLM processing requests before Nov 15
24
BG CWR SWEPI LP Mesa 5-26 store completion equipment, 20 water tanks, additional vehicle parking for the Mesa 5-26 11/15/09 Granted 11/15/09 to 02/07/10 11/15/09 to 02/07/10 WYW 116265 32 109 26 Within Core DA2
25
BG CWR, SG SWEPI LP Mesa 12-33 completion equipment storage & parking 12 hr shift 11/06/09 Granted 11/06/09 to 06/01/10 11/06/09 to 06/01/10 WYW 118165 32 109 33 Within Core DA2
26
BG CWR, SG SWEPI LP Mesa 12-28 construction, drilling, completion, facility 11/15/09 Granted 11/15/09 to 03/31/09 11/15/09 to 03/31/09 WYW 118165 32 109 28 Within Core DA2
27
BG CWR, SG SWEPI LP Mesa 1-27 completion activities 01/01/10 Granted 01/01/2010 to 02/07/2010 01/01/2010 to 02/07/2010 WYW 116265 32 109 27 Within Core DA2
28
BG CWR SWEPI LP mesa 7-29 Pit closure 11/16/09 Granted 11/16/09 to 12/15/09 11/16/09 to 12/15/09 WYW 118165 32 109 29 Within CDA DA 1
29
BG CWR QGM Lovatt Dr Water Ext complete construction, testing, cleanup 11/15/09 Withdrawn 11/15/09 to 11/30/09   WYW 176922 32 109 17,19,30 Completed request before Nov 15
30
BG CWR, BEWinter Questar T-7 reclaim groundwater well location, backfill sump/pit to contain drill cuttings and water spread topsoil, backfill pit, seed 11/20/2009 Granted 11/20/09 to 11/26/09 11/20/09 to 11/26/09 WYW 176987, 176988 33 110 2  
31
BG CWR Ultra T-6 reclaim groundwater well location, backfill sump/pit to contain drill cuttings and water spread topsoil, backfill pit, seed 11/20/2009 Granted 11/20/09 to 11/26/09 11/20/09 to 11/26/09 WYW 176986 31 109 30  
32
BG CWR Questar T-2a reclaim area using hand shovels to remove drill cutings, tire ruts, reclaim 11/20/2009 Granted 11/20/09 to 11/26/09 11/20/09 to 11/26/09 WYW 176983 32 110 12  
33
BG CWR SWEPI LP Nortern Liq Gathering Hook Ups Install pipe racks for LGS, install piping, tubing, cable trays, and installation on the Riverside 6-4, New Fork 7-3, Riversie 8-3, Riverside 13-3, Mesa 12-33, Mesa 12-34 11/25/09 Granted 11/25/09 to 02/01/2010 11/25/09 to 02/01/2010 WYW 118165, 06270, 06286 31,32 109 3,4,33,34 All activities are occuring on the developed pad location , no ground disturbance during daylight hrs
34
BG CWR Chevron Birch Creek 205-14 Erosion control to protect cultural site 11/24/09 Granted 11/15/09 to 11/19/09 11/15/09 to 11/19/09 WYE022644 27 113 15  
35
BG CWR Exxon Fiber Optic Line Install overhead line 11/24/09 denied 11/15/2009 to 11/30/2009            
36
BG R-Y Timber Salvage Timber Wrap up beetle kill tree salvage on Zach Roberts' property 12/02/09 Granted 11/15/09 to 12/12/09          
37
BE roost Ultra Riverside 4-11 Simops Fraccing & drilling out plugs 12/02/09 Granted 11/1/09 to 01/31/10 12/6/09 to 01/31/10 WYW06270 31 109 11  
38
BG CWR Chevron LBU 27, 28A,35, 38 Replace gas fired pumps with electric pumps 12/14/09 Withdrawn 12/7/09 to 12/14/09   WYW 109568X 27 113 22, 27, 35  
39
BG CWR Union Boulder Telecom site Install communication tower on wheels and powerline is access rd 12/17/09 Granted 12/17/09 to 04/30/09 12/17/09 to 02/28/09 WYW 176761 and 176762 31 108 10 This is a temporary tower, ground disturbing activities will only occur for the powerline construction in the access road
40
BG CWR, Raptor WY DEQ Boulder Air Station winter ozone studies 12/22/09 Granted 12/22/09 to 04/30/10 12/22/09 to 04/30/10 WYW 161480 32 108 29  
41
SG, FH, BO,Raptor Encana Jonah field wide block exception exception to coa's of non-active raptor nests 12/29/09 Granted 2/1/10 to 815/10 2/1/10 to 7/31/10 JIDPA       Block exception in the Jonah Infill Drilling Project Area: drilling, completion, production, & reclamation
42
BG, Raptor Ultra RS 3-3 Drilling and Completion Operations 11/15/09 Granted Partial 11/15/09 to 02/28/10 11/15/09 to 02/28/10 WYW 06270 31 109 3 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
43
BG, SG, Raptor Ultra RS 2-2 Drilling and Completion Operations 11/15/09 Granted Partial 11/15/09 to 02/28/10 11/15/09 to 02/28/10 WYW 06270 31 109 2 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
44
BG Ultra RS 16-3 Drilling and Completion Operations 11/15/09 Granted 11/15/09 to 04/30/10 11/15/09 to 04/30/10 WYW 06270 31 109 3  
45
RG, SG, Raptor Ultra RS 5-1 Drilling and Completion Operations 11/15/09 Granted 11/15/09 to 02/28/10 11/15/09 to 02/28/10 WYW 06270 31 109 1 Due to previous and ongoing disturbance in this area
46
BG, Raptor Ultra RS 9-2 Drilling and Completion Operations 11/15/09 Granted 11/15/09 to 02/28/10 11/15/09 to 02/28/10 WYW 06270 31 109 2 Due to previous and ongoing disturbance in this area
47
BG, Raptor Ultra RS 4-10 Drilling and Completion Operations 11/15/09 Granted Partial 11/15/09 to 02/28/10 11/15/09 to 02/28/10 WYW 06270 31 109   Due to lack of raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
48
BG Ultra RS 1-4 Completions Operations 11/15/09 Granted 11/15/09 to 01/01/10 11/15/09 to 01/01/10 WYW 143046 31 109 4 Within Core DA2
49
BG, Raptor Ultra RS 5-2 Construction, Drilling, and Completions Operations 11/15/09 Grant Partial 11/15/09 to 02/28/10 11/15/09 to 02/28/10 WYW 06270 31 109 2 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
50
BG Ultra RS 7-28 Drilling, Completion, and Construction Operations 11/15/09 Granted 11/15/09 to 04/30/10 11/15/09 to 04/30/10 WYW 06286 32 109 28 Within Core DA2
51
BG, SG Ultra MS 10-33 Drilling, Completion, and Construction Operations 11/15/09 Granted 11/15/09 to 07/15/10 11/15/09 to 07/15/10 WYW 06286 32 109 33 Within Core DA2
52
BG, SG, Raptor Ultra MS 15-27 Drilling and Completion Operations 11/15/09 Grant Partial 11/15/09 to 07/15/10 11/15/09 to 07/15/10 WYW 06286 32 109 27 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
53
BG, SG, Raptor Ultra MS 9-34 Drilling and Completion Operations 11/15/09 Grant Partial 11/15/09 to 07/15/10 11/15/09 to 07/15/10 WYW 06286 32 109 34 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
54
BG, SG Ultra MS 9-28 Drilling and Completion Operations 11/15/09 Granted 11/15/09 to 07/15/10 11/15/09 to 07/15/10 WYW 06286 32 109 28 Within Core DA2
55
BG, SG, Raptor Ultra MS 4-34 Drilling, Completion, and Construction Operations 11/15/09 Grant Partial 11/15/09 to 07/15/10 11/15/09 to 07/15/10 WYW 06286 32 109 34 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
56
BG, SG, Raptor Ultra MS 1-33 Drilling and Completion Operations 11/15/09 Grant Partial 11/15/09 to 07/15/10 11/15/09 to 07/15/10 WYW 06286 32 109 33 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
57
BG, SG, Raptor Ultra MS 12-27 Completion Operations 11/15/09 Grant Partial 11/15/09 to 07/15/10 11/15/09 to 07/15/10 WYW 06286 32 109 33 Inadequate raptor mitigation plan/rescind 01/15/10 to write adequate mitigation plan
58
Raptor Town of Marbleton sewer,water line near airport Install a 12 inch water line and a 6inch and 8 inch sewer line 01/21/10 Granted 2/1/10 to 7/15/10 2/1/10 to 7/15/10 WYW 176906 30 111 17,20 Install a 6 and 8 inch sewer line and a 12 inch water line.
59
BG, SG SWEPI LP MS 1-27 completion and flowback 02/01/10 Grant 02/01/10 to 02/20/10 02/01/10 to 02/20/10 WYW 116265 32 109 27 Within Core DA2
60
SG, Raptor, FH, BO BP America Jonah field wide block exception exception to coa's of non-active raptor nests 02/03/10 Grant Partial 2/1/10 to 8/15/10 2/1/10 to 8/15/10 JIDPA       Block exception in the Jonah Infill Drilling Project Area: drilling, completion, production, & reclamation
61
SG,, BG SWEPI LP Mesa 12-28 construction activities, drilling, completions, facility activity 02/08/10 Granted 11/15/09 to 7/15/10 03/31/10 to 4/30/10 WYW 118165 32 109 28 Construction activities, drilling, completions, and facility activity
62
SG, BG, Mbird Questar Mesa 8-19 Construction and dirt work activities, drilling, set surf. Casing & cem. Pipe, etc. 02/08/10 Granted 11/15/09 to 09/01/10 07/15/10 to 09/01/10 WYW 015315 32 109 19 Construction and dirt work activities, drilling, set surf. Casing & cem. Pipe, etc.
63
SG, BG, FH, Raptor, BE WR SWEPI LP N LGS DA2 Numerous N LGS pipelines and LGS well pad hookups 03/01/10 Granted 03/01/10 to 07/31/10 03/01/10 to 07/31/10 many lease #s 32 109 28,29,33,34 and 3, 4, 10, &11 T31. R109W  
64
SG BP America SHB 65,66,67,77,78,80-15 Workover rig installing tubing durring daylight hours 03/12/10 Cancelled 3/15/10 to 3/20/10 3/15/10 to 3/20/10 WYW127749 29 108 15 Workover rig installing tubing durring daylight hours
65
FH Teppco CAB 15-19, CAB 17-30, SAG 73-20 pipeline installation 02/22/10 Granted 3/1/10 to 3/12/10 3/1/10 to 3/12/10 numerous 29 107 20,29,30 pipeline installation
66
SG BG CWR Questar Mesa 9-16 construction cellars, drill, completions production 03/15/10 Granted 03/15/10 to 07/15/10 03/15/10 to 07/15/10 WYW 015317 32 109 16 Within CDA DA 1
67
BG CWR SWEPI LP Pinedale Federal 13-19 excavate and backfill area with contaminated soils 03/08/10 Granted 03/08/10 to 03/14/10 03/08/10 to 03/14/10 WYW 144993 31 108 19 Within DA 3 delineation area, human/wildlife health and safety issue, finish before grouse nesting COA
68
SG BP America SHB 78-15 extend exception dates to account for delay. Workover rig installing tubing durring daylight hours 03/12/10 Denied 3/21/10 to3/31/10            
69
SG BP America SHB 24-15 Workover rig installing tubing durring daylight hours 03/12/10 Granted 3/15/10 to 3/23/10 3/15/10 to 3/23/10 WYW127749 29 108 15 Workover rig installing tubing durring daylight hours
70
SG and BO SWEPI LP Boulder 14-32 coriolis meter installation and tank removal 03/15/10 Granted 03/29/10 to 04/02/10 03/29/10 to 04/02/10 WYW 144944 31 108 32 An approved wildlife monitor will be required to ensure burrowing owls are not disturbed during this activity
71
Raptor,BE, BG Lower Valley Energy Wilson Sub-station power line install Wilson Sub-station power line install, trenching 03/23/10 Granted 4/7/10 to 5/7/10 4/7/10 to 5/7/10 WYW 176952 41 117 23 & 24 Impacts will occur but should not be much greater than impacts from the level of activity that already occurs in the area.
72
SG, BG SWEPI LP Mesa 5-26 Pit closure 04/15/10 Granted 04/15/2010 to 06/30/2010 04/15/2010 to 06/30/2010 WYW 116265 32 109 26  
73
SG SWEPI LP Boulder 8-32 Pit closure 04/15/10 Granted 04/15/2010 to 06/30/2010 04/15/2010 to 06/30/2010 WYW 015316 31 108 32  
74
SG SWEPI LP Rainbow 13-29 Pit closure 04/15/10 Granted 04/15/2010 to 06/30/2010 04/15/2010 to 06/30/2010 WYW 118148 30 107 29  
75
SG, BO Nesting SWEPI LP Rainbow 8-31 Pit closure 04/15/10 Granted 04/15/2010 to 06/30/2010 04/15/2010 to 06/30/2010 WYW 118148 30 107 31  
76
SG. BO Nesting SWEPI LP Warbonnet 13-14 Pit closure 04/15/10 Granted 04/15/2010 to 06/30/2010 04/15/2010 to 06/30/2010 WYW 015314 30 108 14  
77
SG, Raptor JGG Noble 6-24 Construction/installation 4531 feet of 4 in nat gas pipeline 03/31/10 Granted 05/01/2010 to 07/01/2010 05/01/2010 to 07/01/2010 WYW 178625 33 109 6  
78
big game mig corridor Koch Construction James Gravel Pit extraction, crushing, loading, and transportation 05/01/10 denied 05/01/2010 to 11/15/2010 05/01/2010 to 11/15/2010 WYW 175450 34 111 21 and 28  
79
BG CWR, Raptor, SG Nest M&L Marketing Alexander Ranch Topographic ground survey existing 2 track within road access easement 04/21/10 Granted 04/21/2010 to 04/21/2010 04/22/2010 to 04/23/2010 WYW 178575 35 110 5  
80
SG Nesting Yates Petroleum Crop. Highway Federal 27 Seeding all disturbed areas using a drill on and around wellsite 04/20/10   04/24/2010 to 04/25/2010 04/24/2010 to 04/25/2010 WYW 133050 29 107 9  
81
BO Encana SHB 75-34 pit closure 04/19/10   4/28/2010 to 4/30/2010            
82
SG Nesting, BG CWR Ultra Mesa 10-33 Drilling, Completion, and Construction Operations 04/29/10 Granted 04/29/2010 to 11/29/2010 04/29/2010 to 11/29/2010 WYW 06286 32 109 33 Within DA2 Core
83
BG CWR, SG Nest Questar Mesa 7-21 Construction, Drilling, Completion, facility, production lines, dehy facility 04/26/10   05/01/2010 to 07/15/2011 05/01/2010 to 07/15/2011 WYW 015317,015315 32 109 21 Within CDA
84
BO Nest, SWEPI LP Rainbow 8-31 correct erosion issues 04/15/10 Granted 04/15/2010 to 06/30/2010 04/15/2010 to 06/30/2010 WYW 118148 30 107 31 Incorrect work represented in letter, must conduct BO nest survey to conduct work
85
FH Nest, BO Nest SWEPI LP Mesa 11-34 Pit closure 04/21/10 Granted 5/1/2010 to 06/30/2010 5/1/2010 to 06/30/2010 WYW 06286 32 109 34  
86
SG Nest, BO Nest Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/01/2010 to 11/01/2010 05/01/2010 to 11/01/2010 WYW 176896       Sec 7,8,18,19,29,30,32,33 T31 R108; Sec 11,12,13,24, T31, R109;Sec 4, T30 R 108
87
SG Nest, BO Nest Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/15/2010 05/03/2010 to 11/15/2010 WYW 178617 and 178619 TUP       Sec 24 T 31 R109; Sec 19, T31 R108
88
SG Nest, Raptor Nest, BE Nest Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178598       Sec 13, 24, T31 R109; Sec 7, 18 T31 R108
89
SG Nest, Raptor, BO, MP Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178599       Sec 12, 13, 24, T31 R109
90
SG Nest, BO Nest Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/15/2010 05/03/2010 to 11/15/2010 WYW 178601       Sec 18, 19 T31 R108
91
SG Nest, BO Nest Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/15/2010 05/03/2010 to 11/15/2010 WYW 178602 31 108 19  
92
SG Nest, MP, Raptor Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178603       Sec 13, 14, 23, 24, 25 T31 R109
93
SG, MP, BO, Raptor Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178604       Sec 13, 14, 24, 25, T31 R109; Sec 19, T31, R108
94
SG, MP, BO Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178613       Sec 24, 25, T31, R109; Sec 19, 29, 30, 31, 32 T31 R108; Sec 5 and 6 T30 R108
95
SG, MP Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178614       Sec 24, 25, T31, R109; Sec 19, 29, 30, 31, 32 T31 R108; Sec 5 and 6 T30 R108
96
SG, MP, BO Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178616       Sec 13, 14, 24, 25, T31 R109; Sec 7, 18, 19,30, 31, 32 T31, R108; Sec 4, 6, T30 R108
97
SG Nest, Raptor, BE Nest Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010 WYW 178912       Sec 7,8,18, T31 R108
98
SG Nest, Raptor, BO Ultra Boulder CGF #2 LGS Pipeline Installation 04/23/10 Granted 05/03/2010 to 11/01/2010 05/03/2010 to 11/01/2010   33 31 108  
99
SG Nest, raptor, BO SWEPI LP DA3 Coriolis meter install install coriolis meters on 7 pads 06/07/10 Granted 06/07/2010 to 08/15/2010 06/07/2010 to 08/15/2010 WYW 06269, 026025, 144933       Sec 13, 14, 23, 24, and 25 T31 R109 Sec 19 T31 R108
100
BG CWR, SG Nest,Raptor Ultra Mesa 12-27 Drill pipe inspection, 3-5 days, daylight operations 05/27/10 Granted 05/28/2010 to 06/02/2010 05/28/2010 to 06/02/2010 WYW06286 32 109 27 FH 42 and 77 have been inactive this year
101
BG CWR, SG Nest,Raptor Ultra Mesa 4-34 Drilling, Completion, production, pipeline and Construction Operations 05/27/10 Granted 07/01/2010 to 02/28/2011 07/01/2010 to 02/28/2011 WYW 06286 32 109 34 FH 77 has been inactive this year
102
SG Nest, Raptor SWEPI LP T-4 SW and T-4 RW,T-9-RW Install ground water study wells-extension 05/26/10 Granted 06/01/2010 to 07/02/2010 06/01/2010 to 07/02/2010 WYW 176989,WYW 141753       Sec 11 and 12, T31N, R109W, Sec 13, T30N, R107W
103
SG Nest, BG CWR, Raptor Rocky Mountain Power Paradise substation and DE earthwork, excavation of topsoil, construction of substation 05/27/10 Granted for alternate dates 06/10/2010 to 11/10/2010 07/31/2010 to 12/31/2010 WYW 175432, 172153, 176892, 178578 31 109 4 and9 FH 84 has chicks, this area is in DA2 which relieves operators from BG CWR COAs
104
SG Nest, Raptor, BO Nest Ultra Warbonnet wells Reclamation 05/27/10 Granted 06/04/2010 to 06/30/2010 06/04/2010 to 06/30/2010 WYW 016161, 025314, 015316, 144994, 016162, 18039        
105
SG Nest Questar SP 14-32 Construction, setting trench boxes, install cellars, install lines, move drill rig 06/07/10 Deny 07/01/2010 to 07/15/2010   WYW 015315 32 109 14 Sage grouse females & chicks are still using the nexting habitats.
106
SG Nest, BG CWR, FH raptor, Raptor Ultra Mesa 10-35 Drilling, Completion, production, pipeline, construction 06/02/10 Grant 07/01/2010 to 05/30/2011 07/01/2010 to 05/30/2011 WYW 06286 32 109 35  
107
bg cwr, sg nest Ultra Mesa 3-27 Drilling, Completion, production, pipeline, construction 06/10/10 Grant 06/15/2010 to 07/15/2011 06/15/2010 to 07/15/2011 WYW 06286 32 109 27  
108
sg nest,bo nest JGG Water monitoring well Install one water monitoring well, small water well drill rig drill 30ft, casing install and cement 06/15/10 Partial grant 06/29/2010 tp 07/27/2010 07/15/2010 to 08/01/2010 WYW 175472 AM #1 30 108 35 Location within PDA DA 5 within 1 mile The Rocks SG Lek, BO nest has been inactive in last 3 years
109
sg nest SWEPI Mesa 12-28 Drill 3 clusters (16 wells) of conductors 06/17/10 Grant 07/01/2010 to 08/01/2010 07/01/2010 to 08/01/2010 WYW 118165 32 109 28 Location within DA 2 core
110
sg nest SWEPI Stewart Point LGS pipeline tie in construct LGS associated with Stewart Point Tie in, Wyoming one call set pin flags for construction 06/23/10 Partial grant 06/23/2010 to 07/15/2010 06/23/2010 to 07/10/2010 WYW 176950 am1, 176951 am1, 178597 32 109 6,7,8,15,17,21,28 Only the walking survey from the Wyoming one call is permitted.
111
SG Nest, FH Nest Rocky Mnt Power Paradise Substation Des Foundation for transmission dead ends 06/03/10 Grant 06/24/2010 to 07/31/2010 06/24/2010 to 07/31/2010 WYW 175432, 172153, 31 109 4,9 This action will only take 2 days with a special auger and cement truck, minimal disturbance.
112
SG Nest Ultra Water monitoring well Anticline water monitoring well 06/24/10 Grant 07/06/2010 to 07/15/2010 07/06/2010 to 07/15/2010 WYW 015314 30 108 15 Completion of this action was delayed due to occurrence of methane vapors and the drill hole caving.
113
SG Nest SWEPI Water monitoring well Anticline water monitoring well 06/24/10 Grant 07/06/2010 to 07/15/2010 07/06/2010 to 07/15/2010 WYW 141753 29 107 10 Adding and additional study well to this location
114
Burr Owl Nest Encana JF 30-8, 31-8, 18-8 Reclaim Pads 06/28/10 Grant 7/1/12010 to 8/15/2010 7/1/2010 to 8/15/2010 WYW 125944 28 108 NE 1/4 of 8 Exception granted unless owls return
115
Burr Owl Nest JGG Cabot TOT #1 Install 1996 foot pipeline & assorted facilities 06/28/10 Grant 7/1/12010 to 8/15/2010 7/1/2010 to 8/15/2010 WYW 178647 28 109 SW 1/4 of 15 Exception granted unless owls return
116
BE Nest, BO Nest Ultra RS to RB Water Line LGS Pipeline Installation 07/07/10   08/01/10 to 11/01/10   WYW 178649 and 178650TUA 31 109 8, 17, 19 ,20, 30, 31, 32 Exception pending Burrowing owl nesting survey
117
SG Nesting, BO and raptor Nest Ultra RS 3-13, RS 15-14, BO 16-18, BO 4-33, BR 10-33, WB 5-12, WB 12-12, WB 4-23, WB 6-23, WB 7-23, WB 3-22, WB 13-23, WB 5-24, WB 4-25 Reclamation 06/23/10 Partial grant 07/01/10 to 07/31/10 07/09/10 to 07/31/10 WYW 06269, 172598, 015316, 118159, 016161, 015314, 018039, 118157, 016158        
118
FH Nest, BG CWR, BE Nest Rocky Mnt Power Paradise Substation and Upper Green Paradise 230 kV trans line Augering a hole for the 6/21 structure and placing the structure in the augered hole. Surface disturbance of the substation, begin construction of substation. 07/20/10 Grant 07/26/10 to 12/26/10 07/26/10 to 12/26/10 WYW 175423, 176892, 172153, 178578 31 109 and 110 4, 9, 27 most of activities are being conducted at the end of the raptor nesting season, the fledglings are nearly ready to leave the territory, they have been hunting with the adults within the territory